So erstellen Sie Produktivitätseinträge im Bautagebuch-Tool des Projekts.
The Productivity section allows you to track how much material arrives on site and how much is installed. Any "Approved" subcontracts or purchase orders with the Unit/Quantity accounting method will appear here so you can track the installation against the line items in the contract.
#: This uneditable field counts the number of entries in a section (e.g. the first entry created will be # 1, and the second entry will be # 2).
Company: Select the company name from the drop-down menu. Companies must be added to the Directory tool to be selected in this drop-down menu. See Add a Company to the Project Directory.
Contract: Select the approved purchase orders from the Commitments tool that corresponds to the items that were put-in-place.
Line Item (#-Description-Qty Units): Select the applicable line item.
Previously Delivered: If there was a previous delivery of these items/materials, enter the number of items that were delivered to the job site previous to this date.
Previously Put-In-Place: If there your team has already installed or put in place some of these items/materials, enter the total number of these items/materials that were previously put in place on the job site.
Quantity Delivered: Enter the total number of these items/materials that were delivered in on this date.
Quantity Put-In-Place: Enter the total number of items/materials that were installed or put in their final place on the job site on this date.
Comments: Enter any comments that may be needed to further describe the entry.