Ziel

Den Status einer Aufgabe mit der Procore-App auf einem Android-Mobilgerät ändern.

Wichtige Hinweise

  • Required User Permissions:
    • To edit any task, 'Admin' permissions on the project's Tasks tool.
    • To edit a task that you created, 'Standard' or 'Admin' permissions on the Tasks tool. 
    • To edit a task you did not create yourself for which you are the Assignee, 'Standard' level permissions on the Tasks tool.
      Note: 'Standard' level users who are assigned a task that was created by someone else can only add comments or edit the status of the task. The status of the task can NOT be set to 'Closed' or 'Void' by a user with this permission level unless that user also created the task.
  • Additional Information:
    • A task's 'Due Date' and 'Status' fields can also be quickly edited from the Tasks display table.
    • You can also change the status of a task when adding a comment. 
    • When a task is placed into the 'Void' or 'Closed' status, the system will no longer send automated email notifications for that task. 

Schritte

  1. Navigieren Sie mit der Procore-App auf einem Android-Mobilgerät zum Aufgaben-Tool.
  2. Tippen Sie auf die Aufgabe, deren Status Sie ändern möchten.
  3. Tippen Sie auf den aktuellen Status der Aufgabe.

    tasks-android-change-task-status.png
     
  4. Tippen Sie auf eine der folgenden Optionen:
    Hinweis: Diese Aktion aktualisiert automatisch den Status des Aufgabenpostens.
    • Eingeleitet
    • In Bearbeitung
    • Bereit zur Überprüfung
    • Geschlossen
    • Ungültig

 